Eltacon Engineering BV

Oil & Gas

Follow us on:

Eltanews:

Natural Gas Conditioning Station for Germany

Eltacon engineered and manufactured a natural gas station for installation in Germany, designed and build according to the European regulations.

 

The natural gas conditioning station is installed at a power plant, upstream of a gas turbine. The gas is filtered, measured, heated and reduced to the correct pressure. Heating of the gas is done with steam in a double tube safety heat exchanger. During  start-up of the combined cycle gas turbine the gas is pre-heated with an electrical heater.

 

The gas is first cleaned in a one stage coalescer filter. The second step is the measurement of the mass flow with a coriolis flowmeter. Heating is installed to compensate the cooling of the gas by the Joule Thomson effect during the pressure reduction and to heat up the gas 20 °C above the inlet temperature to have margin between the actual temperature and the dewpoint temperature. This heating is done with a double tube (safety type) heat exchanger with hot steam coming from the power plant. The double tube design is based upon a tube within a tube. By doing this there is a safety barrier between the steam and the natural gas.

 

For start-up purpose when no hot steam is available yet, an electrical heater is installed downstream the double tube heater complete with thyristor control panel. Pressure reduction is done with a pilot operated self- acting pressure control valve. As a safety, there are two slam shut devices, one integrated at the pressure control valve and a second as a separate valve upstream the pressure control valve.

 

For more information about  gas conditions stations, please contact us via sales@eltacon.com

error: Please contact Eltacon for more info